Nobody likes a cold joint but they happen. Here are several things one can do- 1- Try to avoid the cold joins in the middle/ other part as applicable of the structure where the load is high. 2-Let the rebar run about 50 cms to 90 cms out of the concrete at the joint so that it can tie up with further pour of concrete easily. 3-Form a keyway in concrete for subsequent pour of concrete , so that it may be locked. 4-Where one cannot reach leave a rough or uneven surface at initial pour. Ultimately a cold joint is a connection point between two pour of concretes.
By
Brajesh Mishra, Construction / Contract Management, UPSSCL
| 01 04 2011 09:31:53 +0000
|
I agree with Mr.Ghosh, wecan not avoid the cold joints because of some obuvious practical reasons.but the possitions of such joints is very very important & beam-column joints are the most carelessly concreted parts.It is advoicable to provide cold joints away from the junctions & with propper care as elaborated by Anjaneyula Reddy....
By
MAYUR MASKE, Lecturer, S.I.T. YADRAV
| 01 10 2011 06:16:05 +0000
We come across various joints especially contraction,expansion or construction joints these joints are unavoidable,but cold joints are avoidable,because it happens in sub structure,within initial setting of concrete and also in mass concreting.By providing Admixtures,Grouting method by using Epoxy resin ,inserting cold twisted bars in ribbed portin but not by sand plastering method,but in thin structures like slabs we are following weathering courses in new proofing method doing multiple plastering using various chemical compounds
By
VIMALAN , Construction-Construction Management, PARSVNATH DEVELOPERS LTD
| 01 09 2011 06:57:18 +0000
Most of you, who have constructed buildings, have built a column lift and then laid the shuttering and reinforcement for the upper floor slab and beams. Then after several days you have poured concrete for the floor. What is the joint between the column neck and the beam but a cold joint? Cold joints are inevitable in concrete construction, only one has to deliberately select the location and take adequate measures to minimise the effect of this discontinuity. Only in some specifically importnt cases one has to try and avoid cold joints, like foundations for vibrating machinery. In all cases of cold joints, it is imperative to prepare the hardened concrete surface properly before pouring fresh concrete to join with it. It is also true that large flat surface construction is not possible without providing construction joints at regular intervals. For vast expanses of such construction, one has to plan for contraction and expansion joints at design stage. Regards
By
Basab Ghosh, General Manager (Operations), Saipem India Project Ltd.
| 01 04 2011 17:46:10 +0000
|