Created by : Rinu P Babu, Projects Planning Manager, Mir Realtors Pvt. Ltd  | 06 10 2011 10:55:39 +0000
Industry : ConstructionFunctional Area : Project Management(Technology)
Activity:  583 views;  last activity : 10 12 2011 09:27:50 +0000

Normally arguments come when a project get delayed. Always there is a tendency to blame contractor alone for the delay.

 
Share
 
 
  Rate : 
 
 
All have equal responsibility based on delay analysis Vs Only Contractor is responsible
13
 
 
 
 
3
10
3
Support   Support
Top Argument
1
0

Proper analysis should done based on progress reports. and should find out who made critical delays


By Rinu P Babu, Projects Planning Manager, Mir Realtors Pvt. Ltd  06 10 2011 10:55:39 +0000
 
0
0
The agreement clauses framed by the client with the contractor, and consultant maters most in execution of the project.if agreement caters of all accountable person other than contractor in the agreement then the float can be the contractor otherwise all are responsible for project commissioning.
By Rajendran Mariagnanam Mariagnanam, Founder and managing partner, Braintrain consultancy services LLP  | 10 12 2011 09:27:50 +0000
0
0
It depends of the type of contract. I have seen in many design and build contracts there is huge delay due to the delay in approval of design drawings from the client. In this case the contractor is eligible for claim. But the bottlenecks caused due to insufficient manpower, and other site related issues are the responsibility of the contractor.
By farhad hamza, Planning Engineer, Saudi Bin Ladin Group  | 08 12 2011 12:20:30 +0000
0
0
Sibasis is very correct.If Govt organization is the client,in 90% of the cases,Ifound,client is responsible. Open the tender documents, each and every responsibility has been put on the contractor, but for his every step, the contractor has to get the nod from the client's officers whose reputations are known to all. Eventually, it is the work which suffers, time wise and quality wise.
By Dipak Bhattacharya, Chief Engineer, A private Ltd Consulting Co. in Delhi  | 08 09 2011 16:52:09 +0000
0
0
All are responsible.
By Chetan Pancholi, Project Engineer, Tamboli Castings limited  | 08 07 2011 06:44:45 +0000
0
0
All are equal responsibility. But i think most responsibility is from client side.
By Sibasis Dash, Project Co-ordinator, Feedback Infrastructure Services Pvt. Ltd.  | 06 22 2011 05:56:35 +0000
0
0
Definitely, Client and its representatives always looking to blame Contractor for any kind of delays related to their projects, but its completely depend on Contractor, how he presents his analysis and how he convince client regarding parties involved for the delay.
By Rohit Thakur, Electrical Engineer-Industrial, Quality Engineering and Software Technologies  | 06 19 2011 04:12:57 +0000
0
0
All are having equal responsibility for the delay of the projects. For a completion everybody is working in their respected roles. So everybody who are working to a project whether it is directly or indirectly, they are responisble for the project. We can table simple blame the contractor only. But delay of the project mainly by the contractor only.
By Durgarao.T , Project Engineer, A N Prakash Construction PMC  | 06 11 2011 06:19:33 +0000
0
0
usually by analysing reason of delay in a project client and contractor will be found equally responsible.From client part non deliberation of decisions,drawings and payment in proper time to contractor are the common facts.On the part of contractor delay in arranging man power and equipments and lack of planing for investment to carry out the project are responsible.In construction we all know time is the essence of a project.
By Sabyasachi Dasgupta, Project Manager, Ajayraj constructions Pvt Ltd  | 06 10 2011 15:49:44 +0000
0
0

Honestly, the blame should be shared by all with more responsibility on the person who is directly responsible for the situation. But, in the Indian scenario this is not always the case. The blame is usually put on the person who is unable to fight back or one who is not ready to use violence or one who is a professional.


By John Jacob, Consultant, confidential  | 06 10 2011 14:57:56 +0000
0
0
Agree with you Kaliyamoorthy sir.
By Muhammed jabir rifai, Graduate in Mechanical Engineering  | 06 19 2011 06:47:32 +0000
0
0

Collective responsibility can not be taken by all. The moment, the contractor is awarded, it is the Contractor prime duty to see that it is managed as per the scheduling & planning & forecast the requirement as required in time. Other elements are , more or less , on advisory role, & not really involved in Ground executions. Any addition / deletion / amendment directed by them , as seen feasible, need to be accommodated & delivered the resulted project in time. Any topsy-turvy situation arise, it is to be taken concurrence of the Consultant & the Client.So, the contractor can not absolve the responsibility in delay of project.


By KALIYAMOORTHY , Oil & Gas Area Coordinator, Undisclosed  | 06 17 2011 04:29:45 +0000
0
0

Once the projected is entrusted,the contractor is in know of the possible hold ups.The construction planning is done accordingly.The synergy so developed has to be followed to maintain the pace of progress.


By Mohammad Bakhsh, Project Leader/Managing Consultant, Freelancer  | 06 12 2011 04:05:14 +0000
Leading Biotech Firm startup.
Viewers also viewed
Do you think smiley faces are appropiate on emails to clients? ;)
 
1253 referals 44 arguments, 11875 views
We say think positive be optimistic. We also say that we should find out our weakness and try to...
 
1812 referals 14 arguments, 261 views
close the sick projects vs revive the sick projects
 
5 referals 12 arguments, 212 views
more...  
Recent Knowledge (4)
WE HAD A GOOD NUMBER OF INVENTORS WITH GREATER VISION ABOUT THE SOCIETY. INVENTORS HERE NEED NOT...
 
2 referals 2 arguments, 97 views
These days as I switch on the tv or radio or look at a hoarding I do feel that power of ads I...
 
3004 referals 23 arguments, 482 views
C vs B
 
0 referals 3 arguments, 51 views
more...  
More From Author
getting a certificate as MBA will do nothing with site management. But Knowledge of subjects in the curriculum will help one to improve thier role in a company.
Normally arguments come when a project get delayed. Always there is a tendency to blame contractor alone for the delay.
Construction projects frequently suffer from delays and are completed later than agreed by the contracting parties.  Substantial financial claims will arise with this circumstance, Contractor, Consultant and employer often argue about the cause of and...