| Topic : Building construction |
|
|
Construction Planning & Management |
Construction Project Management THINKPOT...!!!
|
|
Activity:
160 views;
last activity : 11 22 2010 09:09:43 +0000
|
|
|
|
1
STANDARD REGISTERS AND FILES
2
data management for construction project
3
to fight arbitrations in the site
4
01
5
Arbitration due to lacunae in clauses of Contract Agreement
6
ISSUE LOGS...!!!
|
||||||||||||||||||||||
|
|
1.SITE ORDER BOOK: IT IS THE FIRST MOST IMPORTANT DOCUMENT TO FIGHT ARBITRATIONS IN CONSTRUCTIONCOMPANIES. MANY CLIENT ENGINEERS CHANGE THE SPECS VERBALLY. DONT ENTERTAIN THEM WITH OUT WRITTING IN SITE ORDER BOOK. 2.DEVIATION REGISTER: ALL DEVIATIONS IN BOQ AND SPECS AND THE QTY AND AMOUNT SHOULD BE MAINTAINED AND SIGNED BY BOTH CLIENT & CONTRACTOR. 3.HINDRANCE REGISTER: ANY HINDRANCE DUE TO NATURAL CALAMITY, DELAY IN DRAWINGS, DELAY IN DECISIONS FROM CLIENT SHOULD BE WRITTEN AND DULY SIGNED BY CLIENT. 4. DRAWING REGISTER: IT SHOULD BE MAINTENED AND SIGNED BY CLIENT. ANY SMALL JOB INSTRUCTED BY CLIENT SHOULD BE DRAWN AND SIGNED COPY TO BE FILED AND DETAILS ENTERED IN DRAWING REGISTER. 5. TOLERANCE LIMITS: SOME CLIENTS WILL NOT ALLOW EVEN IS STANDARD TOLERANCE LIMITS. THAT SHOULD BE TAKEN IN WRITTEN. 6. MEASUREMENTS AS PER IS CODE: SOME CLIENTS WILL NOT PAY AS PER IS CODE. THIS CAN BE CLAIMED WHILE ARBITRATION. 7. INCONVENIENCE FACTOR & WORKING UNDER FOUL CONDITIONS: UPTO 50 % EXTRA CAN BE CLAIMED AS PER THE INCONVENIENCE LIKE WORKING UNDER ALREADY CONSTRUCTED BUILDINGS, SEWERAGE AREAS, DOUBLE HEIGHTS, CONTINUOUS SEEPAGE AREAS, SMALL PATCH WORKS, VERY THIN RCC WALLS WHICH REQUIRE SAME AFFORD AS OF HEAVY WORKS AND PAID VERY LESS AMOUNTS. 8. DETAILS OF TENDER: EVIDENCES OF DATE OF TENDER, YEAR OF SSR/BSR CONSIDERED FOR THE TENDER, ALLOTMENT DATE OF WORK, HANDING OVER THE SITE TO THE CONTRACTOR, DETAILS OF PERMITS FROM GOVT. DEPTS. ETC TO BE MAINTAINED.
|
4
|
|
|
whenever a construction dispute is referred for arbitration, the evidence is to be given for the claims made. for example: what are the causes of delay? what are the causes for variations? whether the material used is as per specification? etc. a data base sholuld be maintained. what should be the nature of data? so that the arbitration or dispute resolution is easier nd faster. |
3
|
Pragya, i agree with you, that it is difficult to convince the appropriate authority. but many a times it is observed that the contractor is not mantaining any kind of systematic data base for the project and when his bill are wih held for some reason, he is not in a position to prove his point.
on the contrary i feel that such maintainece of database sholud be made a necessary condition to be fulfilled in the contract conditions it self.
i am doing my dissertation in this topic'' management techniques for minimisation of disputes and claims in building contract''.
Rajeshwari ji i agree with all the points that you have mentioned that should be followed while maintaining a data management for a construction project.But even if all these things are being maintained by contractor can he be sure to win the claim as there still can be problem in conveying your point with appropriate explanations.what do you think?
|
|
It is very important to maintain all written documents in date wise .It is advisable always to take written conformation regarding any discussions. |
1
|
The site should have a dedicated and experienced hand and the team right from the start of the project in the form of an experienced or a professional QS or contract administrator who will study the contract,execution drawings,method sequence and the degree of difficulty or the construction constraints likely to be encountered at site and to notify the client immediately upon realisation of the impediments with time and cost effect it will have on the project by applying for EOT and raising and defending claims through proper generation of authenticated joint records of events.If this is done half the battle is won as there won't be any need to arbitrate when the issue is recognised and reconciable by the Authority.
|
|
The following data is maintained to avoide arbitration. 1, registered the agreement conteining detail specification of item, time limite, project cost, panelty of delay etc 2, dont allow any execution without work order issued by the authority. 3, maintein all the document related to site executation 4, monitor the progress of work compared to CPM chart and issue the notice to contractor if any dely in works. 5, item specification is prepared in such a way that no complication arises while executation of work
|
1
|
|
|
Causes of Arbitration
Building up of a case from the initial stages is a must for winning any Arbitration.May be from the contractor side or the department.The local gazette publications in case of labour,material and fuel rates. Files in evidence of the Correspondance between the contractor and department regarding the issues of arbitration is a must. |
0
|
|
|
ISSUE LOGS refers to a document convering the following details updated during any ISSUES/DISPUTES raised between two parties in a CONTRACT and ISSUES analyzed on a Priotity Basis: |
0
|
|
|
|
|
|
|
contracts are an important part in construction document. these can be outsourced to techno legal consultants who can prepare a detailed contract document. these firms can have technical and legal expertise which can be an added advantage. also these... |
out sourcing is a better option. but it needs more effective and efficient management to handle number of agencies and to deliver projects. each agency brings in its own core expertise which can be very beneficial for quality , quantity and time... |
MIS is one of the important aspect of construction. ERP is used in construction. please mention the areas of implementation of ERP and its benefits. |
