Asked by : Naimish , Construction-Heavy, Gourav Engineers
Industry : Construction
Functional Area : India
Activity: Question posted: 05 15 2008 22:28:14 +0000, 10 answers, 4998 views, last activity 03 24 2012 11:19:35 +0000
 
Share
 
 
  Rate : 
 
 

Assume that machineries required for it are your own.

 
 Top Answer :
Rating : +2 

I) take out the excavation plan

2)check mainly the levels through contour survey

3)add extra 1.5 mtr alround to have the working space.

4)devide the depth of excavation to have the offset projection of 600mm for every 1.6 mtrs

5) Engage the type of the excavating machine for excavation

6)calculate the efficiency of the machine interms of qty excavated against time

7)list out the per day consumption of consumables of the machine.

8)list out the man power consumption of the machine,

9) Now you have the cost required for the consumables and manpower per day.(8 hrs)

10)find out the hiring charges for the machine without item no.7 and 8.

11)cost/unit=9+10/6



[ Delete ]
[ Edit ]
Report Abuse
by   srinivasalu. chintamani, Dy.General Manager(projects),Sunil Mantri Realty Ltd.,  | 05 16 2008 07:18:13 +0000
  Answer modified by     Mohammad Bakhsh, Consultant(Civil), Rail Vikas Nigam Limited  | 03 24 2012 11:19:34 +0000
[ Delete ]
[ Edit ]
Not Rated

Mr Naimish,The objective in developing rate analysis should be to arrive at a figure that, as nearly as possible, represents the cost of the work done under the operating conditions encountered and the accounting system in use.

In the present scenario,you need to work out operating cost.though you can not exclude expenses chargable to machine.ie, cost of machine,capital recovery factor.Interest to capital,life cycle of machine,expenditure on IOH,POH and expenditure on annual machine maintenance and of course, labour/08 hrs. This apart, you must ascertain the estimated quntum of work. Aggregating total expenditure and devide by the approximate quantity to be excavated will lead you estimated  rate per cubic meter. 

Hope, it will help you to brush up your knowledge.

  Answered by     Anita Puneet Aggarwal, Engineer, RCM  | 03 24 2012 05:19:50 +0000
[ Delete ]
[ Edit ]
Not Rated

How many hours for machine /labour we should take

  Answer modified by     Sanjay Sharma, Head of the Department / CEO (Projects), International Infrastructure Company, -3 b US$ Global Business Group Co.  | 07 03 2011 19:07:50 +0000
[ Delete ]
[ Edit ]
Not Rated

Excavation in Soil using Mechanical means of construction

 

  1. Calculation of Quantity – Requires Excavation Plan, provisions as per IS 1200,Use Average end area Method or Grid square Method, Need contour plan of NGL
  2. Rate consists of (1) Labour (2) Machinery (3) Material (4) )Overheads and Profit

 

Before starting rate analysis, Fix & finalise  – Labour, Material, Machinery based on Method of Excavation, Dewatering provisions, shoring and bracing provisions, if required.

 Rate Analysis: (Mechanical Means in Normal Soil): A case

 Step_1 : Assume a out put app. 360 m3

Step-2: Take Manpower Factors i.e. Labour & Supervisor (Mechanical excavation, a supervisor supervises 5000 m3 / day, labour 200 m3/day) and Current rates of Manpower.

Step-3: take per hour rates of Machinery with Fuel and maintenance (outsourcing) OR Work out the rates of machinery as capital purchase - Owning cost, Major/minor maintenance cost, Fuel, oil & Lubricants, Operators cost, depreciation.

Step-4: Work out / Fix efficiencies of Machineries- Hydraulic excavator 0.9 cum bucket capacity, Tipper 5.5 cum capacity etc.

Step-5 :Work out cost of Manpower +Material (Zero) +Machinery

Step-6: take provisions for Dewatering, shoring and bracing , as required.

Step-7 : Take Overhead Charges @ 6-10% ot total of Step-6

Step-8 : Add Profit etc. @ 10-12%

Step-9 Total it and divide by 360, you get Excavation rate / m3. 

Step-10: Disposal…………….later on if required.

 Note: For Rate Analysis, you do not require Quantity to be calculated only Method / Planning of Excavation.

 

Enjoy…………..

  Answered by     P.Srinagesh , Head - Contracts CB Richard Ellis  | 05 19 2008 21:47:06 +0000
[ Delete ]
[ Edit ]
Rating : +1 

* Do the bore holes to know the soil strata to the required depth.

* Take the NGL's

* With the available soil strata depth at different grids, calculate the volume for that particular strata.

* Choose the machinary which is suitable to the particular strata and analyse it's effeciency.

  Answered by     sanjaysharma , Civil Engineer-Highway Roadway feedback  | 05 19 2008 05:13:02 +0000
[ Delete ]
[ Edit ]
Rating : +1 

take the level of top portion the excavated portion.

anlayse the uantity with rate.

calculate the machine efficency i.e no. of hours reuired to finish the job .it involve the deperication of mach. spare parts,men, and then compare it with your rate the try to get maximum profit and efficency.

  Answered by     Maninderpal Singh, Project Manager Madison Holdings FZCO  | 05 19 2008 01:22:39 +0000
[ Delete ]
[ Edit ]
Rating : +1 

I have read some answers above & most of them mentioned the general analysis but one major factor is not mentioned that the productive or the quantity that can be excavated will also depend of the site conditions i.e type of soil, very important the arrangements/ facilities for disposal of excavated material, as this will effect the productive of work & depends on the site conditions.

  Answered by     Ajit , SBU/Profit Center Head LASA India  | 05 17 2008 21:20:27 +0000
[ Delete ]
[ Edit ]
Not Rated

It differs for excavation above ground and in foundation. One has to add costs for benching while doing excavation above ground so also the costs of approaches.

  Answered by     Perugu Shyamsagar, Senior Manager (BUISNESS DEVELOPMENT - T&D), ELECNOR INTERNACIONAL  | 05 15 2008 23:02:42 +0000
[ Delete ]
[ Edit ]
Not Rated

Just go with the 6 Hat Methodology

  Answered by     Shekhar Hanuman Keskar, Civil Engineer-Highway Roadway Afcons Infrastructure Ltd  | 05 15 2008 23:02:18 +0000
[ Delete ]
[ Edit ]
Rating : +1 

1. CALCULATE THE QUANTITY OF EXCAVATION TO BE DONE

2. FINALISE THE EQUIPMENTS TO BE USED

3. CALCULATE THE PRODUCTIVITY OF EQUIPMENTS CONSIDERING THE CYCLE TIME

4. FIND OUT THE FUEL CONSUMPTION AND SPARES NORMS

5. CALCULATE THE TOTAL WORKING HRS REQUIRED AS PER PRODUCTIVITY

6. CALCULATE THE MANPWER COST PER HR

7. FIND OUT THE OWNING COST OF EQUIPMENT AND CALCULATE THE DEPRECIATION AMOUNT PER YEAR.

8. TOTAL COST / QUANTITY = COST/CUM 

 

 

 
JobSite for Investment Banking Professionals
JAVA, J2EE, Webservices, WESB, JSF & Custom Tags & Libraries, JAVA Spring Hibernate Senior Developer, Hyderabad
Linux Admin jobs in bangalore
Viewers also viewed
Load Bearing Construction vs RCC frame construction
 
166 referals 41 arguments, 26626 views
hey i have  completed  diploma in civil engineering, Now i want to do NICMAR course, any one can...
 
29 referals 9 answers, 3192 views
Is it really important that construction organization to have PMP certification, but then...
 
4 referals 38 arguments, 6565 views
more...  
Unanswered Questions (595)
  packers and movers  gurgaon     gurgaon packers and movers packers  movers  gurgaon packers...
 
0 referals 0 answers, 0 views
I saw an advertisement , Flats in Electronic city for 22.3 Lac is it true? Is it the right price?
 
0 referals 0 answers, 0 views
Vashikaran Mantras - Indias leading vashikaran expert+91-7073730429 Vashikaran Mantras - Indias...
 
0 referals 0 answers, 0 views
More From Author
There are various ways to control it. 1. By Providing wather shed in such manner  to avoid direct sun light over the windows. 2. By means of Plantation for G+1 buildings , shadow of the trees should cover the window. 3. By using Insulated double...
E - voting may can help us to increase the voting percentage, Beacause lots of peoples are working far away from their home due to business purpose or due to their job. It has been seen that lots of educated highly educated peoples are not like to got...
We want a good CEO for PM post. Rahul has still  lots to do to become a CEO. He is not the deserving candidate , he needs more experiance  he should progress step by step . Only Gandhi family's surname is not inough to run a country it should be not a...
more...