Build your professional network on facebook via our app Go to app
 
<< Prev  22 of 33 in Topic  Next >>
Topic : Perspectives on Agile Development
  Rate : 
 
Industry : IT Products
Functional Area : Application Software
Activity: Question posted: 01 22 2009 11:31:41 +0000, 5 answers, 360 views, last activity 07 06 2010 20:18:08 +0000
 
Share
 
 
 
 

As Agile methods and its development is the talking point at the moment and the conference which is happening on perspectives of agile development, so this is a better platform to ask question on Earned value and its index and various other aspects in project management. So do help me out here guys!!!

 
 Top Answer :
Rating : +2 

Earned Value at any point measures :

Whether a Work done is

1. Cost --> On Budget, Under Budget or Over Budget

2. Time -->On schedule , Ahead of Schedule or Behind Schedule

3. Actual Cost & Time Efficiency?

4. With Present Efficiency --> How much we shall be spending in future?

5. If to be within Budget --> What efficiency to be attained in Future?

Problem : GOOD CONCEPT, But at what level to be applied, WBS -  Work Package, Summary Level or Activity level???



[ Delete ]
[ Edit ]
Report Abuse
by   M NITIN SHENOY, PMP, IPMA-D, CEng MICE, Manager  | 03 25 2009 13:56:31 +0000
  Answered by     B L'N, Consultant, cgn  | 09 04 2009 13:29:20 +0000
[ Delete ]
[ Edit ]
Not Rated

i see this post is 5 months old; if it is still monitored, here is my reply to Nitin:

EV is monitored at WBS levels suited for the role - Sponsor/developer, Contractor etc. Usually, the Client side monitoring is at Level 3. Contractor go deep. Activity level monitoring is not necessary, in my opinion. Key is setting up control accounts, which are one or more work packages monitored by a organizational element.

I am a certified Earned Value Professional (as I understand, i am currently the only EVP in India)and will be glad to be of assistance in case of queries.

  Answered by     Anuj Verma, PMP, Project Manager, IBM India Ltd.  | 01 23 2009 04:08:50 +0000
[ Delete ]
[ Edit ]
Rating : +2 

The earned value technique measures performance of the project as it moves from project initiation through closure. The Earned Value Management (EVM) methodology provides a mean to forecast future performance based upon past performance.

  Answered by     Arun Sarin, Business Analyst, Oracle  | 01 22 2009 11:51:19 +0000
[ Delete ]
[ Edit ]
Not Rated

Earned Value can be used in almost any project situation and in almost any project environment. It may be used on large projects, medium sized projects, small projects, complex and simple projects and in any market or industry sector. Some people, of course, know all about earned value, they have used it for years - but perhaps not as effectively as they could have done, and the above answer given is right on the button, i agree with vikash on this.

  Answered by     Vikash Jaiswal, Business Analyst, SAP  | 01 22 2009 11:47:58 +0000
[ Delete ]
[ Edit ]
Not Rated

Earned Value is a technique that clearly shows whether you're getting value for the money that is being spent. It is a major component of best practice in Project Management. It is mandatory in USA and Australia and is being used more and more in the UK. The technique essentially identifies the value of the useful work done at any given point, in all areas and at all levels within the project. By comparison with the original plan, Earned Value can be used to identify other parameters such as time to completion, cost to completion and expected final costs. It also enables project managers to identify those areas of the project that are proceeding really well and those that are in trouble and enables percentage progress and performance indices that needs to be calculated. hope this helps dayanand.....

 
Leading Recruitment Firm
Leading Recruitment Firm
Viewers also viewed
close the sick projects vs revive the sick projects
 
5 referals 12 arguments, 212 views
Indian MBA vs International MBA
 
452 referals 18 arguments, 223 views
In todays rapidly changing scenario companies are attracted to those guys who are presentable...
 
1411 referals 38 arguments, 568 views
more...  
Unanswered Questions (32)
More From Author
How convenient it is to blame the government.. There are flaws in government and then there were always flaws there.. now we can see them clearly because many people are coming up and giving voice to the wrong practices..
It is a wonderful concept but we need a right plan to follow it. Just an idea wont help.
Bad news really bad news . 1) We should produce our own arms . 2) More arms means more fight. 3) Only arms would not ensure security.
more...