Build your professional network on facebook via our app Go to app
 
<< Prev  97 of 123 in Topic  Next >>
Topic : Construction Project Management
  Rate : 
 
Asked by : Afaque Akhtar, PMP, KSC
Industry : Construction
Functional Area : Project Management
Activity: Question posted: 01 27 2009 17:12:51 +0000, 14 answers, 4217 views, last activity 01 17 2012 14:58:09 +0000
 
Share
 
 
 
 
 Top Answer :
Rating : +2 

Manpower Estimates depend on only two factors:-

1. Market Rate -  very directly available on market analysis / survey

2. Productivity Rate -  available in CPWD standards - Delhi Schedule of rates

But productivity Rate in reality inturn is depends on the following:

1. Skill Level of Workforces

2. Availability of Material and information to work with

3. Quality measures and Workmanship expected

4. Safety measures in place

5. Risk Factor

6. Environmental Factors

Thus a judicious productivity rate to be assumed for calculating MANPOWER Estimates in a project..!!!



[ Delete ]
[ Edit ]
Report Abuse
by   M NITIN SHENOY, PMP, IPMA-D, CEng MICE, Manager  | 03 13 2009 12:12:19 +0000
  Answered by     shahnawaz khan, QS, Tempus infra projects pvt ltd  | 01 17 2012 14:58:09 +0000
[ Delete ]
[ Edit ]
Not Rated

 1. Productivity rate as available in CPWD schedule.

2. Technical skills of work force.

3. Site condition 

4. Availability of Material,Plant,machinery & equiptmets.

 

  Answered by     Mohammad Bakhsh, Consultant(Civil), Rail Vikas Nigam Limited  | 09 06 2010 02:19:45 +0000
[ Delete ]
[ Edit ]
Not Rated

Almost all Central Government  Departments have their own Schedule of Rates.Apart from that ,all State Governments have updated list of minimum wages/labor rates according to nature of works.Following these schedule of rates may partially help,but not accurately as to satisfy the questionnaire.The best  and accurate methodology is to carry out rate analysis of each activity taking help from these published basic data.This way one may obtain realistic man power estimation.

  Answered by     Murali K Balla, Technical Support Manager Atkins  | 02 22 2010 10:37:08 +0000
[ Delete ]
[ Edit ]
Not Rated

Standard Schedule of Works published by all state Govt and and central agencies give fairly reasonable estimate of manpower and machinery requirement although it is impossible to estimate accurate time.

  Answered by     Pragya Kothari, Construction-Heavy, DLF  | 02 22 2010 08:12:27 +0000
[ Delete ]
[ Edit ]
Not Rated

Hi Afaque, interesting question.

The manpower estimate consists of a listing of the number of direct labor man-days required to complete the various activities of a specific project. They are Builder (BU), Construction Electrician(CE), Equipment Operator (EO), Steelworker (SW),and Utilitiesman (UT).

Thanks.....

  Answer modified by     Mallaya Pandravada, GM-Project , GSSInfraTech Pvt Ltd  | 07 07 2009 09:18:56 +0000
[ Delete ]
[ Edit ]
Rating : +1 

The data for manpower estimation is job specific and region specific.

It also depend on the location of height of the work..Al ways the nature of the manpower estimation changes from Project manager to manager location to location.The location of work may be at restricted area where permits need be taken from time time in petrolium industry:polluted environment; defence establishment where passes to be renewed from time to time. It also depends onthe weather extremely hot or cold or rainy weather.

Every time it is a test to project executive to asses the manpower for the project works.There is no supplimant to the on ground knowledge of the project managers gained on the basis of their vast experience.

Time and motion study is the best way toarrive at the labour constants to assist in manpower estimation.

Yes the constants are very helpful in case of the machinary wherethe environmental influence is less and the estimate of the work hours can be near accurate.

  Answer modified by     SB DIKSHIT, STATE QUALITY MONITOR, U.P.R.R.D.A  | 07 07 2009 05:45:54 +0000
[ Delete ]
[ Edit ]
Rating : -1 

MANPOWER ESTIMATION IS DONE WITH THE HELP OF GUIDELINES GIVEN IN SCHEDULE AND SPECIFICATION DERIVED BY THE BIGGEST ROADWORK INDUSTRY/DEPTT. OF GOVT OF U.P.KNOWN AS PUBLIC WORKS CEPARTMENT, AND IS FOLLOWED BY ALL CONSTRUNCTION AGENCIES/DEPTT.OF STATE,THIS HAS BEEN A OLD METHOD OF ESTIMATION AND FOR EXECUTION OF WORK,BUT NOW WITH THE HELP OF CAD(COMPUTER AIDED DESIGN)

  Answered by     Dhanaraman , Project Manager, CRN  | 04 04 2009 08:46:21 +0000
[ Delete ]
[ Edit ]
Rating : +1 

 It is very difficult to mention any standard and accuate method for estimating manpower as the requirement varies from site to site. It depends on the Project Manager, Site conditions, Quality of work.

Every project manger should maintain the trend record of productivity against manpower by weekly or monthly basis, this will be practical method to get accurate manpower requirement.

  Answered by     anshuman tyagi, Project Planning, HCC  | 04 03 2009 14:35:41 +0000
[ Delete ]
[ Edit ]
Rating : +1 

Man Power  estimation was done on the basis of the norms as per the industry, quality and the type of work. 

These norms has been arrived from past data only.

Like for Tunnelling . we take Driller 0.079 /cum likewise . However the norms can be adjusted as per project.

  Answered by     SRINIVAS CHADA, Consultant, STRATEGIC PLANNING & COST ENGINEERS , MUMBAI  | 03 16 2009 14:06:02 +0000
[ Delete ]
[ Edit ]
Rating : +1 

CPWD and PWD are basedon Historical data , Scientific analysis and regional data . So these are accurate as BENCHMARKS only . However , one has to analyse based on location where project is being executed with the Rate Analysis parameters given by CPWD or PWD .

 
Leader in IT recruiting
Hiring for SAP BW in Pune
Hiring for SAP BW in Bangalore
Viewers also viewed
Project Planning Engineers have a very "Hyped" Important role on Paper roles and responsiblities...
 
0 referals 27 arguments, 4622 views
Who has more chances of being succesfull in a Project Manager's Role in Construction Projects...???
 
104 referals 61 arguments, 4927 views
Normally arguments come when a project get delayed. Always there is a tendency to blame...
 
0 referals 38 arguments, 1304 views
more...  
Unanswered Questions (7)
 
0 referals 1 answers, 0 views
Do You want to Apply for Admission to Chinese Universities? To complete the online application...
 
5 referals 0 answers, 0 views
What all the best way  employee productity can be increased in a software project  ??
 
0 referals 0 answers, 0 views