Asked by : Sachin , Construction-Construction Management, DLF LOR
Keywords : road estimate
Activity: Question posted: 10 21 2009 09:16:14 +0000, 12 answers, 14880 views, last activity 08 13 2014 05:28:36 +0000
 
Share
 
 
  Rate : 
 
 

What sholud be the cost of constructing 1KM of road with
a) RCC ROAD
b) Bitumeous road
including excavation, filling, dressing, topping, reinforcement etc. all complete.

 
  Answer modified by     Tapan Tapu, Junior Engineer, ARSS Infrastructure Projects Limited  | 08 13 2014 05:28:36 +0000
[ Delete ]
[ Edit ]
Not Rated

dear all it shoul be for a flexible road 1.4 crore. per km

  Answered by     Sheik Abdulla, Accounts Manager, Computer operator  | 07 26 2014 08:40:20 +0000
  Answered by     Sheik Abdulla, Accounts Manager, Computer operator  | 07 26 2014 08:40:06 +0000
  Answered by     Balvir Singh, Director Sales, Reality Investments Solutions Pvt.Ltd.  | 07 12 2014 06:54:50 +0000
[ Delete ]
[ Edit ]
Not Rated

if road length is 1000 meter and width is 5.5 meter what will cost in lucknow

Regards,

balvir

  Answer modified by     Revanth Sundaresan, B.Tech/B.E. student, Vivek Vidyalaya High School  | 12 09 2013 08:06:52 +0000
[ Delete ]
[ Edit ]
Not Rated

Could anyone tel me the cost of basic construction for a thar road?

  Answered by     Syed Maktoum, Regional Sales Manager, Dorma India  | 09 02 2012 15:36:37 +0000
[ Delete ]
[ Edit ]
Not Rated

Could anyone please tell me what is the approximate construction cost of base layer and bituminous layer for a stretch of 1 km road in India? I would highly appreciate if anyone can post a break-up of the price for raw materials, gravel, aggregate, machines and tools and labor.

  Answered by     Rajesh Paul, Construction method planning and design & structural design., Shapoorji Palonji & Co Ltd.  | 03 28 2011 05:09:39 +0000
[ Delete ]
[ Edit ]
Not Rated

It will be 70 - 90 Lacs / Km,

  Answered by     Biranchi Narayan Acharya, AGM, Simplex Infrastructures Ltd  | 10 22 2009 13:39:05 +0000
[ Delete ]
[ Edit ]
Not Rated

Well it depends upon purely Trffic load condition,ground condition, geological stratas, topographical situations,resource availability etc. Thus it is impossible to say any cost. It may range from 5 lacs to 5 crores per Km.

  Answered by     Vivek Singh, Project Manager, L&T  | 10 22 2009 10:48:00 +0000
[ Delete ]
[ Edit ]
Not Rated

For flexible pavement it is avg. approx 7 crores per km and for rigid pavement it is aprrox 11 crores per km. This includes everything, structures also.

But this is just a thumb rule.

  Answered by     Sachin , Construction-Construction Management, DLF LOR  | 10 22 2009 04:04:34 +0000
[ Delete ]
[ Edit ]
Not Rated

dear Ananth,

Sholud it not be between 80 lacs to 1 crores

 
Leading recruitment Firm, Permanent Staffing, Temporary Staffing, Executive Search & Selection, and RPO
Aim Plus Staffing Solutions is the brain child of a set of professionals from the HR and technology communities. Established in 2005, Aim Plus Staffing Solutions is the leading provider of Talent Acquisition and Recruitment Process Outsourcing solutions to the Technology, Knowledge Services,......
Viewers also viewed
WE SEE THAT ROADS GET DAMAGED VERY BADLY ,THERE ARE MANY REASONS SUCH AS HEAVY TRAFFIC , BUT U...
 
196 referals 13 answers, 3110 views
We are still talking about Indo-Pak relations. After Osama being found there many tend to...
 
2091 referals 25 arguments, 1570 views
With so many construction happening around getting a construction bid going your way is very...
 
0 referals 4 votes, 2713 views
more...  
Unanswered Questions (283)
In order to understand regarding that switching corporation features properly, subsequently...
 
0 referals 0 answers, 0 views
It's been discovered we now have a few transferring organizations which in turn cost people who...
 
0 referals 0 answers, 0 views
It's been recognized there are a number of shifting firms which in turn cost those with the...
 
0 referals 0 answers, 0 views