As per level sheet, the excavated qty is 100 Cum, same earth will be carting away of 3 km distance, (Since the Carting away is not included in excavation specification, or item) for that how much qty i need to pay for Contractor. whether qty will be increased, or any bulkage factor i need to considered,
people are saying 30% i need to add, that means i need to pay 130 Cum is it right
or 100 Cum i need pay
what is the Standard proceedure, there is any perticular Code other than IS 1200
Prev1NextShowing 1 - 2 of 2
Answered by
ajay , Creative Director, ajay enterprise & company
| 12 14 2010 15:02:11 +0000
Answered by
ajay , Creative Director, ajay enterprise & company
| 12 14 2010 14:59:50 +0000
Prev1NextShowing 1 - 2 of 2
Found the question
"What is the mode of Measurement of Excavated earth Qty and Carting away Qty, "
interesting?
Refer to your connections and communities

Leading recruitment Firm
Excellent communication in English, Associate/Senior Associates, www.delphicjobs.com, Bangalore
Excellent communication skills, Associate, 24/7 Customer, Bangalore
Viewers also viewed
|
|
|
|
|
|
Unanswered Questions (7)
More From Author
HOW TO FIND THE GOOD CONTRCTORS, HOW TO EVALUTE THE CONTRACTORS. WHAT ARE THE FACTORS EFFECT ? |
What is the mode of Measurement of Excavated earth Qty and Carting away Qty, |
Why the Rate Difference between General Excavation and Excavation in Trenches, What are the factors effecting |