Build your professional network on facebook via our app Go to app
 
<< Prev  11 of 12 in Topic  Next >>
Topic : Industrial construction
  Rate : 
Posted in Community :

Construction Planning & Management

 
Industry : Construction
Functional Area : Productivity & Performance
Activity: Question posted: 01 30 2009 13:47:25 +0000, 8 answers, 397 views, last activity 07 06 2010 20:18:08 +0000
 
Share
 
 
 
 
 Top Answer :
Rating : +1 

 I fully agree, CPM is best method for most of the Infrastructure Projects. However, these do not hold for the R&D type of projects. CPM also hold for turn around/ shut down management for process industry , generally involving I/ II & even III crtitical activity.



[ Delete ]
[ Edit ]
Report Abuse
by   Abhijeet Joshi, MANAGER, Oil  | 03 04 2009 16:10:58 +0000
  Answer modified by     M NITIN SHENOY, PMP, IPMA-D, CEng MICE, Manager  | 03 25 2009 15:10:06 +0000
[ Delete ]
[ Edit ]
Not Rated

CPM useful, only in Planning Stage to arrive at Project Duration for Top Mgmt and Client Approvals..

After that, CPM Network gets OBSOLETE as SCOPE changes gets introduced right from Day 1...

[ Delete ]
[ Edit ]
Rating : +1 

Citical Path method is very good way of finding out the activities whc may cause delay to the project end date if fixed. but should be done with a very gud experiance of practical site knowledge & should be the resionable relations. it helps very strongly in EOT 's. As a Planner i really enjoy working with critical path method.

[ Delete ]
[ Edit ]
Rating : 0 

The effectiveness of the CPM relies on how microscopically all the elements have been broken down into. The more detailed the WBS, the more factors and risks are accounted for. The CPM will also give a clear idea of the different available floats which may have to be used as and when the program starts deviating from the CPM. This is a very good technique for use in projects which have a definite start and end, like construction projects.

  Answered by     TIRATH MEWAR, Project Management, Lanco Infratech Ltd  | 02 08 2009 10:53:07 +0000
[ Delete ]
[ Edit ]
Rating : +1 

IT IS ONLY USEFUL WHEN THE EVENT TIME IS PRE-ESTIAMTED, AND NATURE FORCES ARE NOT TAKEN INTO ACCOUNT

  Answered by     Kishor , CEO/MD/Director, ConPro Infrastructures & Developers PVT Ltd  | 02 02 2009 09:18:09 +0000
[ Delete ]
[ Edit ]
Rating : +1 

I agree with Mr.P Sridhar. CPM is used in projects where activity duration and end results can be predicted. Construction industry has known deliverables. So CPM is used extensivley. Research projects uses PERT method wherein one can use probablity and optimistic and pessimistic analysis.

[ Delete ]
[ Edit ]
Rating : +1 

In any project having various activities which are interlinked in one way or the other, the CPM defines the path or sequence over which all critical activities lie.A delay in any one of those activities would result in time over-run and consequently cost over-run too. The top project management have to keep a hawks eye 'mainly on those activities on the Critical Path and also keep a watch to see that non-critical activities do not consume their float and become critical!

  Answered by     P.Sridhar , Construction-Construction Management, Al-Naboodah Construction Group  | 01 31 2009 08:16:58 +0000
[ Delete ]
[ Edit ]
Rating : +1 

Cretical path Mentod (CPM) is used for projects mainly the the activities duration can be assed from the previous exprience , i mean the duration can be estimated most suitable for construction projects

 
 
Viewers also viewed
Construction project scheduling is a topic that has received extensive research over a number of...
 
391 referals 18 votes, 3624 views
In the civil works industry – where competition is fierce, and profits margins are razor thin –...
 
486 referals 13 votes, 449 views
Environmental problems have been considered as a serious situation in construction. Waste...
 
55 referals 10 votes, 1360 views
more...  
Unanswered Questions (108)
More From Author
I guess it will not decrease the weight of the metal because due to the increased weight of the oxygen which has combined with the iron......    But sides are not relevant !! 
Kannan good debate but can you make you sides more clear. And one way is to reuse the wasted cements. Most of the people they don't reuse it and leave it like that. 
more...