What sholud be the cost of constructing 1KM of road with a) RCC ROAD b) Bitumeous road including excavation, filling, dressing, topping, reinforcement etc. all complete.
|
|
Biranchi Narayan Acharya
| Answered
| 2 years ago
|
|
Well it depends upon purely Trffic load condition,ground condition, geological stratas, topographical situations,resource availability etc. Thus it is impossible to say any cost. It may range from 5 lacs to 5 crores per Km.
|
|
|
|
Sachin
| Answered
| 2 years ago
|
|
dear Ananth, Sholud it not be between 80 lacs to 1 crores
|
|
Answer: "What is the cost of constructing 1KM of road ?" deleted from your view.
|
(rate this)
|
What sholud be the cost of constructing 1KM of road with a) RCC ROAD b) Bitumeous road including excavation, filling, dressing, topping, reinforcement etc. all complete.
|
|
Biranchi Narayan Acharya
| Answered
| 2 years ago
|
|
Well it depends upon purely Trffic load condition,ground condition, geological stratas, topographical situations,resource availability etc. Thus it is impossible to say any cost. It may range from 5 lacs to 5 crores per Km.
|
|
|
|
Sachin
| Answered
| 2 years ago
|
|
dear Ananth, Sholud it not be between 80 lacs to 1 crores
|
|
Answer: "What is the cost of constructing 1KM of road ?" deleted from your view.
|
(rate this)
|
I am wokring on a master plan ( housing Project ) for a private developer. Now the client has asked for a Store Management Procedure. I am not aware what is this exactly all about.
Answer: "What is Store Management Procedure?" deleted from your view.
|
(rate this)
|
Since i am from Building line and now working in an architect's office on master paln, where i am assigned the job to study/ paln roads for an area of 100 acres? Kindly guide me with books/ codes etc...
|
|
SB DIKSHIT
| Answered
| 2 years ago
|
|
Dear Sachin,  For latest pl. go through Institution of Engineers, better become member and Indian Road Congress codes,membership shall be very helpful for roads.I f u want to go deeper in buildings ,u should go for national building...
|
|
|
|
SB DIKSHIT
| Answered
| 2 years ago
|
|
SINCE U ARE VERY CLOSE TO DELHI ,U CAN VISIT THE OFFICES VERY EASILY.HAVE THE CURRENTÂ CATALOGÂ OF ALL THESE,INSTITUTION OF VALUERS IS ALSO INÂ DELHI.
|
|
Answer: "What are common codes/ reference books for designing/ planning roads in huge master plan?" deleted from your view.
|
(rate this)
|
|
|
Sachin
| Answered
| 3 years ago
|
|
Refer analysis of Rates 2004 Volume 1 from Nabhi Publications ( it is a Governament Book) - it is not a government book dear
|
|
|
|
aditya
| Answered
| 1 year ago
|
|
analysis of rate 44 Glorious Years of Nabhi Publications Welcome to Analysis Of Rates Compilation of Analysis of Rates and Estimation Techniques for Civil Works 2010 (In 2 Vol)  The 4th revised and enlarged edition provides analysis of rates...
|
|
Answer: "How much add for scaffolding in Brick work & Plaster work ?" deleted from your view.
|
(rate this)
|
Should we deduct the the volume of lintels from brickwork over door openings ?
|
|
kota siva rama prasad
| Answered
| 3 years ago
|
|
if the area is less than 0.5 sqmt deduction is not required, if it is more than required
|
|
Answer: "Deductions in brickwork" deleted from your view.
|
(rate this)
|
Is it 10% of basic rates ?
|
|
ashish palsuley
| Answered
| 3 years ago
|
|
First fix the basic labour rates of all the items to be executes for ground floor. Then add 10% lift charges for each floor on basic rates.i.e. 10% for first floor, 20% for 2nd floor on basic gf rates. Cost of materials has nothing to do with the...
|
|
|
|
SB DIKSHIT
| Answered
| 2 years ago
|
|
In UPPWD there is a schedule of rates and analysis of rates as a printed materials in which taking the Mr. Ashish derivation has been done and resulted to final figures ,rates of labor and materials is revised from time to time whenever it...
|
|
Answer: "How to prepare extra rates of lift charges for reinforcement, shuttering , plaster etc." deleted from your view.
|
(rate this)
|
|
|
Sachin
| Answered
| 3 years ago
|
|
DLF LOR - 200
|
|
|
|
Brajesh Sharma
| Answered
| 3 years ago
|
|
Darpan check out this link- http://toostep.com/insight/layoffs-soar-as-india-plunges-deeper-into-recession This will give you the numbers what you are asking for. Regards, Brajesh sharma.
|
|
Answer: "Count of laidoff employee's in companies we know?" deleted from your view.
|
(rate this)
|
|
|
Charles davison
| Answered
| 2 years ago
|
|
Harnam,I feel The steel for slabs @80-100 looks high unless we are taking flat slabs into account,beams can be a little higher at 350kg/m3
|
|
|
|
Sachin
| Answered
| 3 years ago
|
|
I think what you have given may be applicable for residential but for commerical i think it sholud be 5.5 to 6 kg/ sq.ft
|
|
|
|
Er. Harnam Singh
| Answered
| 2 years ago
|
|
4-4.5 kg/sq feet is for residentail but for commercial may be more in the ramge of 5-5.5 kg.sqfeet Memeber wise column will have 225-250 Kg.cum , Beams 225-250 kg/cum and slabs will have 80-100 kg/cum ( Per cum of concrete)
|
|
Answer: "what are the thumbrules for calculating various building materials in Commercial building like steel, cement, shuttering..." deleted from your view.
|
(rate this)
|
|
|
Charles davison
| Answered
| 2 years ago
|
|
Harnam,I feel The steel for slabs @80-100 looks high unless we are taking flat slabs into account,beams can be a little higher at 350kg/m3
|
|
|
|
Sachin
| Answered
| 3 years ago
|
|
I think what you have given may be applicable for residential but for commerical i think it sholud be 5.5 to 6 kg/ sq.ft
|
|
|
|
Er. Harnam Singh
| Answered
| 2 years ago
|
|
4-4.5 kg/sq feet is for residentail but for commercial may be more in the ramge of 5-5.5 kg.sqfeet Memeber wise column will have 225-250 Kg.cum , Beams 225-250 kg/cum and slabs will have 80-100 kg/cum ( Per cum of concrete)
|
|
Answer: "what are the thumbrules for calculating various building materials in Commercial building like steel, cement, shuttering..." deleted from your view.